This section outlines the usual sequence of events for scheduling preventive maintenance.
Tasks can be scheduled by date, by meter reading, or by a combination of both (for example, an oil change every three months or 3000 miles, whichever comes first). MainBoss also has facilities for seasonal scheduling (for example, inspecting air-conditioning equipment every month during summer, but not in winter).
Projected manpower schedules do not include tasks that have been scheduled according to meter readings—there is no good way to predict exactly when a meter will reach a particular value. However, MainBoss will tell you when a meter reaches a value where preventive maintenance is required. (For more about how MainBoss handles meter readings, see Meters.)