The Quick Outside Facility

< Previous section  |  Table of Contents  |  Index  |  Next section >

The Quick Outside facility is a fast way to create a new purchase order so you can charge materials or labor to an outside contractor. It's intended to let you record a lump sum labor cost or a single material item from an outside source. If you need to record more detailed information or a lot of materials, create a full purchase order and link it to the work order.

Note: For more about purchase orders, see Purchase Orders.

You start the Quick Outside facility by clicking Quick Outside in the work order editor. This opens a window that contains the following:

Dummy Purchase Orders: Some users may use Quick Outside as a way to create dummy purchase orders—purchase orders that will never be sent to a vendor but which are created to keep MainBoss's records complete. In this case, you may want all the dummy purchase orders to have the same order number (for example, PO 00000) so they aren't confused with real purchase orders.

To get this effect, you want the "P/O Number" field to be filled in with the number you choose for dummy purchase orders. You can do this by typing the number manually, or you can use Save Settings to save the settings for the window (including the standard dummy number). For more information on Save Settings, see Saving Settings.