Man Hours .75
Items to Check & Initial Completion:
1.___ Clean unit and make visual examination of all parts.
2.___ Operate from limit to limit. Observe operation, look for binding,
sluggishness, action of limits, etc.
3.___ Determine if valve seats and holds properly.
4.___ Check condition of packing.
5.___ Check condition of dials and positioners.
6.___ Apply graphite to moving parts of valve.
7.___ Lubricate motor and gear box as necessary.
8.___ Inspect contacts, brushes, motor, controls, switches, etc. Clean and
adjust as necessary.
9.___ Clean up work site.
Tools & Materials:
1. Standard Tool Kit Plus Pipe wrenches to 24"
Tubing cutters
Flaring tool
Small acetylene outfit
Packing tool kit and packing
3/4" socket set
Crescent wrenches to 14"
2. Cleaning equipment and materials. Consult the Material Safety Data Sheets
(MSDS) for hazardous ingredients and proper personal protective equipment
(PPE).
3. Lubricants. Consult the MSDS for hazardous ingredients and proper PPE.