Man Hours 1
Special Instructions:
The work required by this procedure may cause the activation of an alarm and/or a
supervisory signal. The field office manager and the control center or fire
department that will receive the alarm and/or signal must be notified prior to
start of work. This guide establishes one extra check point to be performed once
each month on all fire pumps that are equipped with automatic starting features.
(See Inspection FPFPMP-W).
Items to Check & Initial Completion:
1.___ Alter environmental condition programmed to start fire pump, such as
reducing water pressure or causing water flow by opening bypass or drain
valves, etc. This method will prove automatic starting of fire pump on drop
in water pressure.
2.___ Clean up and remove all debris from work area.
Tools & Materials:
1. Standard Tool Kit