Man Hours .5
Special Instructions:
The work required by this procedure may cause the activation of an alarm and/or a
supervisory signal. The office manager and the control center or fire
department that will receive the alarm and/or signal must be notified prior to
start of work. (See FPAUTOFDCT/AL-A).
Items to Check & Initial Completion:
1. ___ Clean track.
2. ___ Lubricate all pulleys.
3. ___ Inspect for damage, worn and binding cable or chain and
proper threading through pulleys.
4. ___ Replace fusible links and other heat actuated devices that
have been painted. Check operation of heat actuated devices
other than fusible links.
5. ___ Replace damaged or stretched cables or chains and adjust to
proper length.
6. ___ Check counterweight for proper suspension.
7. ___ Operate door by disconnecting or lifting counter-weight, or
other appropriate means.
8. ___ Check for proper fit in binders and tight fit of wedge
against stay roll. Inspect stay roll for wear.
9. ___ Check for breaks in face covering of doors.
10.___ Examine tin-clad and kalanein doors for dry rot.
11.___ Inspect all hardware for damage or wear.
12.___ Clean up work area and remove all trash.
Tools & Materials:
1. Standard Tool Kit