Man Hours 1
Special Instructions:
On first inspection, check that:
(1) all air terminals (lightning rods) are interconnected, and;
(2) at least two down conductors are installed with their own ground
connection.
Items to Check & Initial Completion:
1.___ Inspect air terminals for corrosion and rigid attachment to structure.
2.___ Examine conductors for corrosion, strong mechanical joints which provide
good electrical conductivity, and loose or broken fasteners.
3.___ Check for loops, sharp bends (less than 8" radius) and frayed horizontal
and vertical conductors.
4.___ Check for damaged guards and down conductors.
5.___ Inspect grounding attachment for permanency and corrosion
(if practical).
6.___ Test resistance to ground for each down conductor.
7.___ Clean up work area and remove debris.
Tools & Materials:
1. Standard Tool Kit
Plus Insulated pliers and screwdrivers
Wire strippers
Wire crimpers
Voltmeter - Ohmmeter - Milliammeter
Clamp on meter(volt - ohm - amp meter)
Soldering kit
1/8" 25' fish tape
Burnishing tool